New Furniture and Finishing Touches (20 April 2017):
Re-occupation Day, and Bits-and-Pieces (15 April 2017):
Just About Complete (6 April 2017):
Complete - Apart From the Servery Hatch and Snagging Details (31 March 2017):
Plumbing Complete, Pipe Boxing Underway (21 March 2017):
Cooker In-place, Flooring Done, Doors Being Fitted (12 March 2017):
Kitchen Units Fitted; Start Made on Internal Doors (8 March 2017):
Kitchen Being Fitted; Plus Lots of Other Jobs (7 March 2017):
Canopy Constructed, Kitchen Floor Laid & Kitchen Arrives (2 March 2017):
Finishing Touches to the Block Paving and Topsoil Arrives (17 February 2017):
External Paving Underway, Painting and Fit-out Continuing (15 February 2017):
Interior Painting Starts, and Getting Ready for External Paving (10 February 2017):
External Work Continues, Lots of Progress Internally (08 February 2017):
External Work Progresses (03 February 2017):
Floor Main-Screed Completed, External Work in Progress (27 January 2017):
Floor Screed Started and Electricity Reconnected (24 January 2017):
Plastering Completed, Floor Insulated (20 January 2017):
So Bright and Airy (11 January 2017):
Internal Scaffolding Coming Down & High Ceilings Plastered (10 January 2017):
Steady Progress Over the Christmas/New Year Holiday Period (03 January 2017):
Interior Walls & Wiring Progressing Well (21 December 2016):
Doors & Windows are Fitted (13 December 2016):
Borough Mayor and County Councillor Make a Visit (10 December 2016):
The External Scaffolding is Down (09 December 2016):
Velux Windows are in, and Gutters are being fitted (02 December 2016):
Tiles are on and the Interior Takes Shape (28 November 2016):
Getting Ready to Tile (23 November 2016):
Roof Woodwork Progressing Well (19 November 2016):
Work Has Started on the Roof (15 November 2016):
Apart From the Eaves the External Walls Are Up (8th November 2016):
External Walls Near Completion (4th November 2016):
(Photos courtesy of John Breese)
The Walls Are Growing Quickly (1st November 2016):
Brick Work Progresses (28th October 2016):
Bricklaying Has Started (25/26th October 2016):
Ready for the Bricklayers (18th October 2016):
The Floor Gets Underway (7th & 11th October 2016):
Steelwork Frame Complete (4th October 2016):
Steelwork for the New Building Arrives (3rd October 2016):
Building Project - Footings Completed and Drainage Being Installed (27 September 2016):
Building Project - Work Continues on the Foundations (19 September 2016):
Building Project - First Concrete has been Poured (14 September 2016):
Work Starts on the New Building (12 September 2016):